    Nanzih freeway link will be completed by end of 2028, deputy mayor says

    Opinion: Ko Chih-en must find her own way through the election fog

    Kaohsiung councilor Lin Chih-hung challenges KMT’s Ko over cash payment timetable

    Facebook X (Twitter) Instagram Threads
    Kaohsiung Times
    Saturday, October 10
    Facebook X (Twitter) Instagram
    • Latest
    • Kaohsiung
    • South
      • Pingtung
      • Tainan
      • Chiayi
    • Crime
    • Business
      • ESG
      • Technology
      • Energy
      • Real Estate
    • Politics
    • Lifestyle
      • Sports
      • Health
      • Entertainment
      • Travel
    • Long-form
      • Editorials
      • Formosa Files
      • Article Series
      • Books
    • Youth
    Kaohsiung Times
    • Latest
    • Kaohsiung
    • South
    • Crime
    • Business
    • Politics
    • Lifestyle
    • Long-form
    • Youth
    Home » Kaohsiung plans 19-station Green Line — but it might take 30 years
    Urban Future September 23, 20264 Mins Read

    Kaohsiung plans 19-station Green Line — but it might take 30 years

    Proposed route would connect eastern districts with hospitals, stadiums and the existing MRT network
    Share
    Facebook Twitter LinkedIn Email Copy Link Threads

    By KHT Staff. Images via KH MRT Bureau, NextApple News.

    KAOHSIUNG — Kaohsiung is studying an 18.3-kilometer MRT Green Line that would connect several of the city’s fastest-growing eastern districts, although a new report warns that passengers could wait as long as 30 years before riding it.

    The preliminary route would include 19 stations across Zuoying (左營), Renwu (仁武), Niaosong (鳥松), Fongshan (鳳山) and Siaogang (小港), according to NextApple News.

    However, the project remains at an early planning stage. No construction budget or opening date has been approved, and the city has not yet submitted a feasibility study to the central government.

    NextApple said the proposed line could take as long as three decades to complete when feasibility studies, environmental reviews, route approval, land acquisition, detailed design and construction are considered. The 30-year figure is an estimate rather than an official city timetable.

    The route shown in preliminary planning materials would begin near the proposed Purple Line’s P6 station in the Fushan area and travel through Kaohsiung Veterans General Hospital, the Siahai redevelopment area, and Renwu’s Baguoliao and Chengde communities.

    It would then continue toward the National Museum of Indigenous Peoples, the Chengcing Lake Baseball Stadium and Kaohsiung Chang Gung Memorial Hospital. A possible connection with the Yellow Line is shown near its planned Y3 station.

    The route would continue through Fongshan, where planners have studied a station near Caojin Road with underground connections to Taiwan Railway’s Fongshan Station and the Orange Line’s O12 station.

    Earlier proposals avoided central Fongshan because of the difficulty of making sharp turns through the built-up district. The latest concept uses part of a former Taiwan Sugar railway corridor to create a more workable alignment, according to NextApple.

    Proposed “Blue Line” from Fongshan to Chengcing Lake area.

    From Fongshan, the line would travel toward Fongshan Stadium, Jhonglun Industrial Park and the Yellow Line’s planned Y20 station before continuing through the Jhongmin public housing area, the Chung Cheng Armed Forces Preparatory School and Fongding Road.

    Its southern section would cross the Provincial Highway 88 corridor and terminate around the Dingjhuang, Jhong-an and Gueilin communities in Siaogang.

    Planning documents identify six social-housing projects, three redevelopment areas, three high schools, two major hospitals, two sports facilities, a museum and an industrial park along the proposed corridor.

    The five districts contain a combined population of approximately 850,000. That figure describes their total population, however, and should not be interpreted as a ridership forecast or the number of people living within walking distance of the proposed stations.

    Proposed “Cyan Line” running north on MinZu Rd. to the HSR Station.

    The new concept is considerably more ambitious than an earlier Green Line studied by the city. In 2022, the proposed route covered only 5.73 kilometers between Minzu Road and Zuoying High Speed Rail Station and included 10 stations.

    City officials have since expanded the concept to address transportation gaps in eastern Kaohsiung, where large residential areas and major public facilities remain outside convenient walking distance of the existing Red and Orange lines.

    Proposed “Pink Line” from MinZu Rd. to Lotus Pond.

    A recent suggestion from City Councilor Tsai Wu-hung (蔡武宏) would extend or connect the line toward Kaohsiung International Airport and the Red Line. Such a connection would not replace the Red Line’s existing airport service, but it could give residents of eastern Kaohsiung a more direct route and reduce the need to travel through central Kaohsiung to transfer.

    The MRT Bureau said the line’s final southern alignment would depend partly on the airport’s future development. Officials have also identified land near Fongding Road as a possible depot site because few sufficiently large parcels remain available along the corridor.

    Proposed “Grey Line” from Benguan Rd. to Lotus Pond.

    Neither the airport connection nor the depot location has been approved.

    The Ministry of Transportation and Communications has said it is waiting for Kaohsiung to complete and submit the project’s feasibility study. Even if the line advances, it would still require central-government review, funding approval, and several additional planning stages before construction could begin.

    For now, the Green Line is best understood as a long-term proposal rather than the city’s next confirmed MRT project.

    Featured Hero Kaohsiung MRT Kaohsiung MRT Yellow Line Kaohsiung redevelopment Kaohsiung transportation
    Share. Facebook Twitter Threads LinkedIn Email Copy Link

    Related Posts

    Nanzih freeway link will be completed by end of 2028, deputy mayor says

    October 8, 2026

    Kaohsiung councilor Lin Chih-hung challenges KMT’s Ko over cash payment timetable

    October 8, 2026

    Beyblade X and Pokémon tournaments scheduled for Double Ten holiday

    October 8, 2026
    Add A Comment

    Comments are closed.

    Nanzih freeway link will be completed by end of 2028, deputy mayor says

    October 8, 2026

    Kaohsiung councilor Lin Chih-hung challenges KMT’s Ko over cash payment timetable

    October 8, 2026

    Beyblade X and Pokémon tournaments scheduled for Double Ten holiday

    October 8, 2026

    A green light can still lead to a fine at Kaohsiung intersections

    October 7, 2026

    Takao Rock brings 20 acts to three free stages this weekend

    October 7, 2026

    Nanzih freeway link will be completed by end of 2028, deputy mayor says

    Opinion: Ko Chih-en must find her own way through the election fog

    Kaohsiung councilor Lin Chih-hung challenges KMT’s Ko over cash payment timetable

    Beyblade X and Pokémon tournaments scheduled for Double Ten holiday

    A green light can still lead to a fine at Kaohsiung intersections

    Takao Rock brings 20 acts to three free stages this weekend

    Facebook X (Twitter) Pinterest Vimeo WhatsApp TikTok Instagram

    News

    • Local
    • Business
    • Sports
    • Politics
    • Opinions
    • Lifestyle
    • Health

    News

    • Entertainment
    • Travel
    • Formosa FIles
    • Books
    • Technology
    • Youth
    • Latest

    Company

    • Information
    • Advertising
    • Contact Info
    • Privacy Policy & GDPR
    © 2026 Kaohsiung Times. Developed by Second Space.
    • Privacy Policy
    • Terms
    • Accessibility

    Type above and press Enter to search. Press Esc to cancel.